Installation requirements for water ring pump line
In the use of water ring vacuum pump in the process of the installation of equipment, but the correct installation is the premise of guarantee the normal work in the future, so during the installation process should pay attention to what we should pay attention to the problem?
(1) derusting, cleaning and assembling of water ring pump equipment:
1. Before installation, the anti-rust oil or dry oil applied on the processing surface must be cleaned and cleaned. Before installation, the rusty parts should be thoroughly removed before assembly.
2. All pipelines on the equipment should be cleaned and kept unimpeded.
3. Be familiar with the drawings and understand the equipment structure before the assembly of the machine parts.
4. When assembling the equipment, it shall first check the appearance shape and dimension precision of the parts and assembly, and confirm that it meets the requirements before assembling.
(2) installation of water ring pump:
1. Before the pump is in place, check the base size, position and elevation to meet the design requirements.
2. The car is flexible, without block, stuck phenomenon and abnormal sound.
3. The horizontal and vertical water level of the pump foundation shall not exceed 10/1000, and the machining surface shall be taken as the benchmark when measuring.
4. Before connecting the motor to the pump, the motor should be separately tested for steering, current, voltage and insulation performance, and then connected after confirmation.
5. The driving shaft and driven shaft should be aligned. After connecting, the car should be checked.
6. After the pump is connected to the pipeline, reset to find the correct situation. If the connection is not correct, it should be adjusted immediately.
(3) installation requirements of water ring pump pipeline:
1. The inside and end face of the pipe shall be clean, and the sealing cover and screws shall not be damaged.
2. Use flange bolts and pipe joints to find the pipe center, and do not force connection.
3. After the pipe connected to the pump, should no longer be on them to defend and gas cutting, such as the need to defend or gas cutting. Should remove the piping or take necessary measures. To prevent slag into the inside of the pump or pump parts.
(The article comes from the Internet. If reprinting is not allowed, please contact our company to delete it.)